2nd Floor Walls

The 2nd floor walls are each lifted from the ground to the 2nd floor using a forward-reach forklift.

First, place the wall panel on the forward-reach forklift.

Deposit the wall panel on the 2nd floor.

Carry the wall panel to its proper place.

Stand-up the panel (carefully !). Don't let go !

Keep doing it for all 17 wall panels.

Leave out the last 2 wall panels so that the roof trusses can be lifted up easier.

Click on any picture for larger version.